New build development in Greater Manchester of 36 houses split between four house types.

GDV: £8,570,000

Work on site commenced: January 2018

Status: Under construction

Fund Raises/Investor return:
Phase/Fund Raise 1- 10%
Phase/Fund Raise 2- 10%
Phase/Fund Raise 3- 9%
Phase/Fund Raise 4-9%
Phase/Fund Raise 5- 9%

Investor capital repaid: to date no investor capital has been repaid as work on site still continues.

Sales updates:

2 plots reserved (as of March 2019).

March 2019 Build Update:

Plots 1-3 (the properties at the front of the development) have progressed very well since the last reporting period:

– Our contractors have completed plasterboard and skimming works internally

– They have also commenced installing the fitted kitchens and are currently on with 2nd fix plumbing and heating (making sure that they’re properly fitted etc.)

– Our contractors have also progressed with internal decoration and continue to work on the joinery, tiling and installation of the front doors

-Contractors have also made great progress on the external works of the developments: installing steps to the rear gardens and forming the access road behind the plots.

February 2019 Build Update:

– Now that the windows are fitted and the roof is on plots 1-3, the block is watertight and we can commence work inside.

-The joiners have commenced with erecting the timber studwork and the rooms are taking shape. The plumbers and electricians have commenced with their first fix work as you can see by the cables and pipework in the images below.

– The plastering contractor will soon commence with boarding and skimming the plots so that our plumbers, joiners and electricians can second fix (skirtings, architraves, fixtures and fittings) the plots ready for decoration.

– The ground floors have been screeded (levelled  in preparation for floor finishes)

– All drainage, gas, water and electric (services) have now been connected

– Plots 4-36 are currently awaiting the completion of drainage systems.

–  The foundations are complete on plots 21-33 and are awaiting completion of drainage works.

January 2o19 Build Update:  

-Building work for plots 1-3 of the development fronting Micklehurst Road are progressing to plan and internal work is scheduled to be completed by mid-April. You can see these properties in the picture recently taken below.

-On plots 4-36 (the main site of the development) the main drainage system is being established. This complicated process sees the drainage system being installed at two points on the site. Foundation works that had commenced to plots 4-36 will be placed on hold until the main drains have been installed as no heavy machinery will be able to access the site during this period.


Most Recent Development Images: