New build development of 36 houses split between four house types

GDV: £8,570,000

Work on site commenced: January 2018

Status: Under construction

Investor return:
Phase 1- 10%
Phase 2- 10%
Phase 3- 9%
Phase 4-9%
Phase 5- 9%

Investor capital repaid: N/A

Sales update: 2 plots reserved (as of February 2019).

Build update:  

-Building work for plots 1-3 of the development fronting Micklehurst Road are progressing to plan and internal work is scheduled to be completed by mid-April. You can see these properties in the picture recently taken below.

-On plots 4-36 (the main site of the development) the main drainage system is being established. This complicated process sees the drainage system being installed at two points on the site. Foundation works that had commenced to plots 4-36 will be placed on hold until the main drains have been installed as no heavy machinery will be able to access the site during this period.