Alderley Edge, HCD-2

Things are progressing well on the penthouse and we hope to have it completed by the end of November at the very latest. Once we are ready, we will commission photographers to take new pictures in order to help sell it. Plots 3 & 4 will complete by Christmas.  Pictures attached are of some of the completed works over the last month, including a high spec, state-of-the-art kitchen.

If you would like to see the latest images, click here.

 

 

 

 

 

 

 

The Woodlands

The Woodlands, HCD-3

The Woodlands is now occupied by 3 new families.

We are hoping that plots 18, 24, 25, 27, 28  will complete by Christmas.  In total this will bring over £1 million pounds back into the development.

In a bid to drive further sales, we are now revamping our marketing brochures, carrying out sales incentives and changing agents to aid with the remaining plot sales. We are still confident that all properties on the site will sell for the value required, and continue to do all that we can to be proactive as possible.

If you would like to see more click here

 

 

 

Bank Chambers, HCD-5

Bank chambers has now completed on 7 of its 9 apartments.

Of the two remaining apartments, 1 is on the market and the other is being actively marketed by 2 agents. There has already been strong interest, so we expect this to be gone by Christmas. The freehold sale of this development is expected soon, bringing the project to a close.

 

Springfield, Coppenhall Way, Sandbach HCD13

Units are now completed and snagged.  We have just appointed two new agents and are expecting a continuous trickle of viewings to help push sales.

development update

Library House, Frodsham HCD-14

Velux rooflights have now been installed as per the photograph to the left, whilst work on the roof is ongoing.

All addresses are now registered with Cheshire West Council. Brick and blockwork is now complete and window installation is currently underway. Internal staircases are now complete and first fix plumbing/electrical work is in progress. The show apartment is due to be handed over to us at the end of November and fully fitted before Christmas.

You can view the latest images here

 

 


Buckton View, Mossley HCD-15

Plots 1-3 are progressing with brickwork and installation of floor joists as per the construction programme. The remaining plots (4-36) have commenced with piling and foundation work. Drainage work will commence as soon as United Utilities’ approval is received.

You can view the latest images here

 

 

 

Moss Farm, Leighton HCD-16

Completion of purchase due imminently following an administrative error within easement documentation.

Parkside, Sandbach HCD-17

All houses are now build complete. All mains services are now connected and hard landscaping work to block paving, driveways and roads are now underway.

To view the latest images click here

 

 

 

 

Fox Owl Rise, HCD-19 (formerly known as Egyptian Mill)

Our contractor is currently carrying out sheet piling work to the site to assist with the formation of roads and drainage work. Cut & fill work is being carried out to establish site levels prior to construction. Once this work is complete we intend to finish access roads, drainage and continue with foundations.

To view the latest images click here

 

 

 

 

 

 

Bridge View, Rudheath HCD-20

Drainage work is ongoing and piling is due to commence 20/11.