New build development of 28 detached and semi-detached houses

GDV: £6,426,000

Work on site commenced: June 2016

Status: Under construction

Investor return:
Fund Raise/Phase 1- 10-12% (investor capital currently being repaid as of March 2019)
Fund Raise/Phase 2- 10%

Investors capital repaid: We commenced paying phase 1 capital January 2019 – we are continuing to repay capital as sales progress and investors are emailed when it is their turn to have their capital returned.  Please note sales of some of the earlier units have been used to fund the final work on the site in order to not have another fund raise.

Sales update: 7 plots sold, 7 reserved, 1 exchanged (as of early March 2019)

The site should be fully complete by mid April 2019 with contractors off site by that date.

February 2019 build update:

– 13 homes completed and doors locked. A number still waiting on kitchens but are otherwise complete.
– The wall at the front entrance to the build is now complete. The gate is now installed.
– Street lighting has now been installed.
– Formation of gardens is ongoing

January 2019 build update:

-The show house is now completed.
-The majority of plots are nearing completion. 10 of the plots are awaiting kitchens and bathrooms.
-The front entrance wall/gate is under construction.
-Road and driveways complete.
-Formation of gardens ongoing.

Image: